Glass truck along side South Wing installing glass in that area at One Blue Bird Square .
Steel studs and PVC fresh water and sewer drain pipes on first floor of One Blue Bird Square,Olean,N.Y. 14760 Volume 1 .
Looking southwest at exterior of three angles of basement elevator shaft , only one side in view . A pile of sheet rock and steel studding thru out basement and building supplies .
First floor plumbing in between steel studs on first floor and a pile of sheet rock with tools laying on top of them .
South wing,shows concrete of rolls wire mesh all rusty,waiting to be used and a lot of wood frame cartons laying about the floor area on first floor and only floor of south wing .
Page 42 . Basement elevator entrance .Blue plastic hangs down from under first floor . Shows scaffold set up for working on elevator door entrance and a coat hanging on end of scaffold . The workers are finishing up blocking up elevator door entrance .
Web site down for the last two days . This is the third day. But is up and running today and will have to make up a couple of blogs . This one 241,240 and 242 in the following plus a few more days,to get ahead of these web site break downs .
Basement water system , with water gauges installed. The water system is completed now .
Northwest passenger entrance ,with trash laying all over the snow covered ground. Scaffold set up in front of northwest side and shows the sofit in white and blue plastic on west side of building .
North east front corner of west Lauren and North Union streets
East wing glass installation and signs put up for office space for rent .